HST on holdbacks and progress billing in Ontario: when you owe it

Charge HST on the whole invoice. You owe the HST on the held-back part later, when the customer pays the holdback or the holdback period ends, whichever comes first. An application for payment is not an invoice.

Last updated: · Published by Ashbridge Tax · How we write our guides

Quick answer

Charge 13% HST on the full invoice. You owe the HST on the part your customer pays now when it is paid or due.

If a law or a written contract for work on real property provides for a holdback, and the customer keeps it back, you owe the HST on the held-back part later. That is when the customer pays the holdback or the holdback period ends, whichever comes first.

Who this page is for

This page is for an Ontario electrician, plumber, HVAC owner or other trade contractor who is registered for HST. You bill a job in stages, or your customer keeps back part of each payment. You may be a sole proprietor or a corporation. The rules are the same.

The same rules apply if a general contractor holds money back from you as a subcontractor.

It is not for these readers:

See Price, Start Free if you want HST filing priced for your corporation.

Contents

When do you owe HST on a progress payment?

The timing rules are the same in every province. They sit in the federal Excise Tax Act (ETA). In Ontario the rate is 13% (CRA RC4058).

HST on each progress payment is payable on the earlier of two days: the day the customer pays it and the day it becomes due. This is the general ETA rule for any taxable supply. (CRA, GST/HST and home construction; ETA s. 168(1).)

The payment is due on the earliest of three days:

So an invoice dated 10 February puts the HST in the period that holds 10 February, on the part not held back, even if the customer pays in April. (CRA, what to include in your return.)

An application for payment is not an invoice. On many jobs you first send an application for payment. The customer or its consultant checks the work and certifies the amount. You then issue the invoice.

CRA says your application is only a request to assess the work and issue a certificate. It does not treat it as an invoice. (CRA, GST/HST and home construction.) So the application date starts nothing. The clock starts on the day the customer pays or the first of the three days above, whichever comes first.

A late final invoice does not delay the HST. Take a written contract to build, renovate, alter or repair real property. Say you have substantially completed the work, and the customer has not paid or nothing is due yet.

The HST is then payable by the end of the month after the month you substantially completed the work. CRA generally treats work as substantially complete at 90% or more. (ETA s. 168(3); CRA, GST/HST and home construction.) This rule does not apply to a holdback.

CRA also says a progress payment is not a deposit. A deposit is security for a future obligation. The HST on a true deposit is payable on the day you apply it as a payment. (CRA, GST/HST and home construction.)

When do you owe HST on a holdback?

A holdback is part of a payment that the customer keeps until the work is satisfactorily done. Your invoice usually shows HST on the full amount. The deferral is in your return, not on the invoice.

The HST on the holdback is payable on the earlier of two days: the day the customer pays you the holdback, and the day the holdback period expires. CRA says this holds even if you already issued an invoice and charged the HST on the holdback. (CRA, GST/HST and home construction.)

The rule needs one of two things. A federal or provincial law provides for the holdback. Or a written agreement for construction, renovation, alteration or repair of real property provides for it. (ETA s. 168(7).) The page title on canada.ca speaks of home construction, but this wording covers a renovation or a unit fit-out too.

What is the holdback period? The Act says the tax is payable on the day the held-back part "becomes payable". CRA writes "the day the holdback period expires". CRA does not define the period.

The Act's test is the day the holdback becomes payable to you. That is the date your contract or the law sets for paying the holdback. Read your contract for that date. Ontario's Construction Act sets the holdback rules for many jobs. This page does not cover them.

When HST is payable on progress payments, holdbacks and deposits

Part of the job HST payable on the earlier of Level Source
Progress payment, on an invoice The day the customer pays it, or the day it becomes due (invoice date, the date you should have invoiced, or the contract's payment date) Federal CRA, modified 23 Dec 2025; ETA s. 168(1), s. 152(1)
Application for payment Nothing starts here. CRA does not treat it as an invoice. Federal CRA, modified 23 Dec 2025
Work substantially complete, not yet paid or due (not a holdback) Payment or due date, or the end of the month after the month the work was substantially completed Federal CRA, modified 23 Dec 2025; ETA s. 168(3)
Holdback (law or written contract) The day the customer pays it, or the day the holdback period expires Federal CRA, modified 23 Dec 2025; ETA s. 168(7)
True deposit The day you apply it as a payment Federal CRA, modified 23 Dec 2025

Worked example: one job, three invoices, one holdback

All numbers below are made up. They show the steps, not your result.

Assumptions.

Line by line. HST is 13%. Ten percent of an invoice holds ten percent of its HST.

Quarter What happens HST you owe HST if you remit on the invoice
1 Invoice 1 $3,510 $3,900
2 Invoice 2 $4,680 $5,200
3 Invoice 3 $3,510 $3,900
4 Holdbacks paid (period ends the same day) $1,300 $0
Total $13,000 $13,000

The total is the same. The right-hand column pays $1,300 early. By the end of quarter 3 you have collected $11,700 of HST in cash, because the customer kept $1,300 back.

If you remit on the invoice, you pay CRA $1,300 that you have not been paid yet. You wait until November to get it from the customer. This is a cash cost, not a penalty.

Each return is due 1 month after the end of its quarter. (CRA, reporting periods and deadlines.)

The application-date trap. On another made-up job, you send an application for payment on 28 March for $20,000 plus HST. The consultant certifies it. You issue the invoice on 3 April. The HST on that amount is $2,600.

It falls in quarter 2, because the invoice is dated in April. It is not a quarter 1 item, unless the customer paid in March or your contract made payment due in March.

What changes the answer

  1. No holdback provision, or the customer does not use it. A customer who pays in full gets the general rule, even if the contract allows a holdback. If your customer holds money back, make sure the contract or the law provides for it.
  2. The contract holds back part of the price before HST. The customer then pays you all the HST now. HST you collect goes in the return for the period you collect it. (ETA s. 225(1).) The holdback deferral does not help you then.
  3. The holdback period ends before the customer pays. The HST is payable on the end date. You can owe HST on money you have not received. Put the end date in your calendar.
  4. The customer disputes the work. The holdback exists until the work is satisfactorily done. If the customer withholds for a dispute or a lien, the date it "becomes payable" can be unclear. Ask before you decide that the period has not ended.
  5. You call a progress payment a deposit. CRA says progress payments are not deposits. A true deposit is payable on the day you apply it as a payment. The label does not change the date.
  6. You finish the job but invoice late. Say the work is substantially complete in June and you invoice in September. HST on any part not paid or due by 31 July becomes payable on 31 July. Holdbacks follow their own rule.
  7. You use the Quick Method. The Quick Method changes what you remit and what you claim. This page does not cover it. Ask your accountant before electing the Quick Method if materials make up a large share of your invoices.

Common mistakes

Next steps

  1. Read your contract. Find out whether it provides for a holdback, how much it holds, and when the holdback is payable to you.
  2. Put the holdback end date in your calendar as an HST date.
  3. In your books, split each progress invoice into "HST payable now" and "HST payable at holdback".
  4. For the part not held back, find the earliest of these dates. That date sets the HST period.
    • The day the customer pays.
    • The invoice date, or the day you should have invoiced.
    • The contract's payment date.
    • On a written contract for work on real property, the end of the month after the work was substantially done.

See Price, Start Free

The quote prices bookkeeping with HST filing for your corporation. You enter your details and see a price before you commit.

Sources

Price First

You Can See the Price and the Work Before You Pay a Dollar.

Exact price. No preliminary call. No surprise invoice.

See Price, Start Free
See Price, Start Free